Government Property Agency : Cabinet Office

Provision of Whitehall Boiler Systems Relagging Project

Publication Platform
Crown Commercial Service

Publication Date
25 May 2021

Deadline
4:00pm, 22 March 2021

Tender ID
CCZG21A02.

Winners
ENGIE SERVICES LIMITED

Description
Government Property Agency (GPA) requires a Contractor to replace lagging to 2000m of pipework on the Whitehall Boiler System (WBS) during the "summer period" of April to September 2021. Net Zero is the UK Government's statutory target for at least a 100% reduction of UK Greenhouse Gas Emissions (GHG) by 2050, against 1990 levels. In June 2019, secondary legislation was passed that extended that target to "at least 100%". If met, this would effectively mean the UK would end its contribution to global emissions by 2050. According to the Committee on Climate Change's most recent report to Parliament, significant work is required to be undertaken for the UK to achieve its targets.